Factory Change ITSP Flow

Library: Track & Trace Documentation Library
Document: Factory Change ITSP Flow
Version: 1
Effective date: October 1, 2023
Source: Track & Trace Documentation Library
Original length: 10 pages

Contents


1 Standard Description

This document describes the complete process of a Factory change implementation in the IT Service Portal (ITSP).

2 Document Objectives and Benefits

2.1 Objectives

The objectives of the document are:

  • Describe the process and stages of ITSP change
  • Provide the necessary checklist to be filled

2.2 Benefits

The document helps to identify steps to implement a Factory Setup within ITSP.

3 Definitions

Abbreviation / termExplanation
CRCorporate Repository
SAPPrimary global ERP system used in JTI
3PLThird-party logistics
WBSWork Breakdown Structure
QAQuality Acceptance: Test environment
PPRPre-production environment
PRDProduction environment
UATUser Acceptance Testing

Please refer to IT Glossary in the IT P&P portal for further definitions.

4 Roles & Responsibilities

#ActivityGSC CPIT BTS TTGDC TTMarket / Factory
1Define and maintain standardRA/RRC
2Apply the standardRA/RRC

Role indicators:

IndicatorMeaning
AAccountable
RResponsible
CConsulting
IInformed

5 Factory Change ITSP Process Overview

The table below provides a brief overview on the stages within ITSP and the high-level activities to be performed by the teams:

#ITSP Change StageHigh-level Activities
1Preliminary Analysis and EvaluationPrepare Functional Evaluation by BTS
1Preliminary Analysis and EvaluationPrepare Technical Requirements by GDC-TTDC
1Preliminary Analysis and EvaluationAdd Technical Requirements by other teams
2ApprovalGet Approval
3Planning and ImplementationImplementation
4TestingTesting
5Deployment and Close OutDeployment and Close Out

5.1 Preliminary Analysis and Evaluation Stage

In the preliminary and evaluation stage, functional and technical requirements are prepared by IT BTS, GDC-TTDC, and other teams that are required to provide input.

In this stage, manual tasks may also be created for specific tasks, for example:

  • Factory review or local IT impact
  • Network evaluation
  • Server sizing validation
  • Other technical reviews and evaluations by GTC teams or TSC
#CTASK TitleCreation TypeFlag / TriggerResponsibleDeliverables
1.1Initial assessment and dispatchAutomaticCR createdIT BTSCheck the correctness of the assigned team and person
Set the proper service, CI, and other required fields
1.2Perform functional evaluationAutomatic1.1 closedIT BTSFRS document Part I and Part II with functional requirements and business data
Risk and Impact assessment—check all necessary flags
Cost and Workload assessment
1.3Coordinate Support EvaluationAutomatic1.2 closedIT BTS, GDC-TTDCManual task creation and follow-up of all tasks by BTS
Consolidation of all inputs by BTS
Reviewing Cost and Schedule accordingly by BTS
Cross-checking with BTS by TTDC
1.4Financial tasksAutomaticNot specifiedIT BTSGet the quotations and fill the PO-required field
Approvals from Budget owner and ITSP contract
1.5Development EvaluationAutomatic1.2 closedGDC-TTDCFRS document Part III—technical requirements
Recommended solution field filled; from this point, other teams will contribute to this field as well

5.1.1 Task Generation Based on Field Selection

The following field selections during the evaluation stage will automatically generate a CTASK for the respective action:

Field selectionSelected valueAutomatically generated action
Dev. coord. pre-assess required?YESTask for the IT Development Coordinator group defined in CI setup
Development Impact/AssessmentYESTask for development evaluation
Tech. coord. pre-assess required?YESTask for server or network assessment
Enterprise Architecture ImpactYESTask for the Development Center Group defined in CI setup

Other fields in the Impacts tab and the Risk and Impact tab shall be checked by IT BTS to determine if there are other necessary technical tasks to be requested.

5.1.2 Technical Requirements Analysis by Technical Teams

The following are technical requirements that are analyzed by the various technical teams.

5.1.2.1 Technical Infrastructure Teams

  • Local Factory IT—manual
  • Data Center Architecture
  • Data Center Service Delivery
  • Network
  • Technical Integration—manual

5.1.2.2 Others

  • Enterprise Architecture
  • QA team necessary—manual
  • IT Security
  • Training
  • Development
    • Subtasks for different teams and vendors if necessary—manual
    • DevOps if necessary—manual

5.2 Approval Stage

In the approval stage, FRS approval and Team Lead/IT Approval must be completed to proceed to the implementation stage. These approvals are located in the Approvers tab.

#Approval TitleCreation TypeFlag / TriggerResponsibleDeliverables
2.1FRS ApprovalManual1.3 closedIT BTSFRS review and approval
2.2Team Lead Approval, IT ApprovalAutomatic1.3 closed, CI and Processing Type combinationIT BTSCHG review and approval

5.3 Implementation Stage

In the implementation stage, IT BTS/GDC-TTDC is tasked to coordinate any functional, development, or network tasks to deliver the change within planned cost, schedule, and resources to the test QA environment.

For any development, IT BTS/GDC-TTDC must create a new development task. Other specific technical and coordination tasks may also be created as necessary.

#CTASK TitleCreation TypeFlag / TriggerResponsibleDeliverables
3.1Co-ordinate implementationAutomatic2.2 completedIT BTSCoordination of all required tasks to deliver the requirements as planned

5.4 Testing Stage

In the testing stage, IT BTS/GDC-TTDC is tasked to coordinate the migration of the changes to the test environment.

#CTASK / Approval TitleCreation TypeFlag / TriggerResponsibleDeliverables
4.1Migration to QAAutomaticDevelopment CTASK completedIT BTSGDC-TTDCCoordination of migration and testing activities
4.2Co-ordinate testing, training, and communicationAutomatic4.1 closedIT BTS/GDC-TTDCCoordinate and inform the training process and testing activities
4.3UAT ApprovalAutomatic4.2 closedIT BTS/GDC-TTDCCoordinate the UAT approval with the requestor

Source preservation note: The responsible party for task 4.1 appears as IT BTSGDC-TTDC in the extracted source, without a separator. It is retained as published rather than silently corrected.

5.5 Deployment and Close Out Stage

In the deployment and close out, IT BTS is tasked to coordinate:

  • Deployment of the requested change to the production environment
  • Setup of integrations and parameters
  • Announcement publishing of the deployment to end users
#CTASK TitleCreation TypeFlag / TriggerResponsibleDeliverables
5.1Migration to PROD & Go-liveAutomatic4.3 completedIT BTSCoordination of deployment activities
5.2Post-Implementation ReviewAutomatic5.1 closedIT BTSPublish announcement and study the lessons learned

5.6 Change Closed

Once the Post-Implementation Review CTASK is closed, the change request is closed automatically.

6 Document Control

6.1 Contact Person

07/25: Questions and feedback regarding this standard should be submitted to Merve Calis.

6.2 Revision History

VersionEffective datePurpose of changeAuthor
1October 1, 2023First version of the documentSean Policarpio

7 References

  • ITSP Change Management
  • EGP T&T Implementation - IT Activities Coordination Masterfile